|
1
|
|
|
2
|
- System Overview
- Storm Preparation & Restoration
- The Hurricane Season of 2004
|
|
3
|
- 24,000 megawatts of capacity
- 37 sites in the Carolinas, Florida and Georgia
- Diverse mix of generation resources, including nuclear, coal and
oil-fired, natural gas-fueled and hydroelectric plants
|
|
4
|
- 1.5 Million Customers
- 35 Counties
- 20,000 Square Miles
- 145 Million Feet of Wire
- 937,713 Poles
- 200,812 Transformers
|
|
5
|
|
|
6
|
- Design Principles:
- Staged response to storm events
- Defined structure for strategic and tactical activities
- Adaptable to all storm events (hurricane, ice/snow, thunderstorms)
- Employee storm roles
|
|
7
|
- Centralized support:
- resource mobilization
- damage assessment
- staging and logistics
- Storm modeling:
- storm category
- wind speeds
- track
- line miles exposed
- Local focus on restoration and customer service
|
|
8
|
|
|
9
|
|
|
10
|
- 1300 on-system Company and contractor line personnel (Including 268 PEC)
|
|
11
|
|
|
12
|
|
|
13
|
- 1st: Assess the Damage
- Verify what’s out
- Validate resource needs
- Establish restoration times
|
|
14
|
- 2nd: Work the priorities
- Critical customers
- Biggest bang for the buck
|
|
15
|
- Emergency
Operations
Center support
- Proactive press engagement
- ETR establish-
ment and
refinement
- Minimizing bill estimation and
non-pay notice interruption
|
|
16
|
- 125,000+ outage calls per hour
- 250 Call Center Reps
available
24/7 -- plus
- 500 corporate volunteers
- Florida & Carolina resources
- Storm restoration status
provided is Real-Time
|
|
17
|
- The customer service representative inputs the outage information into
our Customer Service System (CSS) database
|
|
18
|
- Customer Service System converts the information into an electronic
outage and transmits to the Outage Management System (OMS)
|
|
19
|
|
|
20
|
|
|
21
|
|
|
22
|
|
|
23
|
|
|
24
|
- 700 miles of transmission lines out of service.
- 83 substations out of service.
- 630 structures down or damaged.
- Most of the transmission damage was concentrated to the path of
Charley’s eye as it traveled from Wauchula to Fort Meade, Lake Wales, up
to the Orlando area.
|
|
25
|
|
|
26
|
|
|
27
|
- 1131 miles of transmission lines out of service.
- 105 substations out of service.
- 211 structures damaged.
- Most of the transmission damage was minor in nature when compared to
Hurricane Charley.
- However, a much broader area of the transmission system was exposed to
damage by Hurricane Frances.
- Restoration strategy was the same as for Hurricane Charley, except on a
broader scale.
|
|
28
|
|
|
29
|
|
|
30
|
|
|
31
|
|
|
32
|
- 853 miles of transmission lines
out of service.
- 86 substations out of service.
- 75 structures damaged.
- Most of the transmission damage was similar to Frances.
- Damage was spread over the entire grid.
- Restoration strategy was the same as prior storms.
|
|
33
|
|
|
34
|
- 6,518,947 feet (nearly 1,235 miles Primary and Secondary wire)–
equivalent of distance between Orlando and Portland, Maine
- 62,979 Insulators
- 6,664 Utility Poles -more than 50 laid miles end to end
- 6,005 Transformers (overhead and underground)
- 327,184 Splices (used to reconnect severed lines)
- 565,000 gallons of gas
|
|
35
|
- Always consider equipment and conductors energized
- Never attempt:
- Pulling meter
- Opening a fused cutout
- Moving downed conductor (lines)
- Please secure site for public and first responders safety
- Company Employees are trained and have proper protective equipment to do
the work safely
|
|
36
|
|
|
37
|
|